|
. Charlie Bugeja worked on the laying of tiles in the toilets at the radio room level while Salvu Magro completed the installation of the water system at this level. Simultaneously to this, more work was being carried out by Carmelo Magro, Frankie Mifsud and Salvu Magro on the installation of the electrical system at ground floor level.
. On March 27, Martin Formosa completed the sculpturing of the decorative emblem of the secondary facade. The bulkier blocks were reduced in size on the bandsaw thereby eliminating unnecessary hardship in lifting.
. On Tuesday, March 2, work was started on the laying of the tiles, with geometric design, in the St. George Hall. This work continued until Saturday, May 6, when the central part of this hall was completed.
. On Saturday, May 6, the sculptured blocks making up the decorative emblem of the secondary facade were lifted, together with Stiefnu' s winch, onto the roof. Stiefnu' s winch is used in the lifting of individual blocks of the emblem into position without the use of much effort.
. The following day, Sunday, Joseph Aquilina resumed with the work of plastering the balustrade and the radio room. In addition, Salvu Magro and Michael Farrugia resumed work on the installation of the water system. More volunteers worked on the laying of the blocks making up the decorative emblem of the secondary facade among whom were Baskal Ellul, Michael Aquilina, Martin Formosa, Joe Zerafa and Karmenu Borg.
. On Friday, May 8, Salvu Magro together with his son Carmelo Magro did the bulk of the work in connection with the installation of the electrical system in the bar area. Martin Formosa initiated work on the first finial which will eventually find its place, together with thirteen other identical finials, on the top-front of the building, above the balustrade. When installed, these finials will signify the completion of all the work related to the entire facade of the building.
. On Sunday, May 13, work on the laying of the decorative emblem of the secondary facade was completed, Salvu Magro carried on with more electrical and drainage .work. Work of a tidying nature was also done.
. The following Sunday, the decorative emblem just installed was grouted while Joseph Aquilina did more work on plastering and grouting of the facade. The first finial was placed in its final position to one side of the emblem.
. Joe Spiteri erected the shuttering, later to be filled with concrete, as an extension of the existing concrete block for the flagpole. The concrete was donated by the Minister of the Ambient and Infrastructure, Architect Ninu Zammit.
. On May 28, the decorative emblem was given the final retouches and the scaffolding around it was removed. Additional scaffolding was put up in order for Joseph Aquilina to be able to plaster the underside of the upper balcony.
. The rest of the marble floor in the St. George Hall was now completed. Work of a preparatory nature was initiated in connection with the laying of the marble slabs on the upper part of the main staircase.
. While plastering and grouting work on the facade resumed, more finishing work was done on the bands around the door and window openings of the St. George Hall. Some building equipment was removed from the bar area in preparation for the festive season.
. On Sunday, June 11, Michael Aquilina continued with work on the main staircase while Joseph Aquilina continued with the plastering of the balconies. Preparations and the necessary consultations were made with the carpenter in connection with the installation of the main front doors. Some concrete, which was later covered with liquid membrane by Michael Farrugia, was poured in the balconies as a precaution against water seepage.
. On Monday, June 12, the (ferrobattuto) handrails were installed on the stairs on the roof. The marble tiling of the Committee Hall has now been started.
. In the week that followed, the floor of the Committee Hall was completed while the marble in the kitchen adjacent to the St. George Hall was also finished.
|