|
In fact on Sunday 15th, June, Martin Formosa worked out the first slab under the supervision of Innocent Centorrino who prepared the detailed drawings. In between, Joe Spiteri, Carmel Magro and others removed the shutter from under the stairs and this was cleaned and put away. Peter Caruana and his group continued laying the inner walls of the back rooms and these were brought to the level of the beam, which supports the roof.
On 12th October 2003, work was initiated on the Doric entablature. This work is more complicated and the degree of finesse in it is higher than that of the Tuscan type. The people who carried out this work were Martin Formosa and Anthony and Marlon Aquilina and John Spiteri. The first stone to be formed was that of the south corner of the secondary facade.
On Sunday, October 19, steel beams were placed in position using the Stiefnu Zerafa winch. Additional work on the entablature was carried out.
The following week, Joe Spiteri erected the shuttering of the concrete beams which were later to be poured on November 16.
Up to Sunday, October 26, three stone blocks of the entablature were completed and which were later to form part of the secondary facade. Mikiel Aquilina worked on the steel reinforcing of the window openings.
By using a 60 ton crane with a capacity of 60 tons, the concrete beams were poured together with the insoles which will ultimately have to support the pre-stressed concrete planks of the roof. This work started at 3.00p.m. and involved the use of some seven cubic meters of C30 concrete mixture. The design and other details of the marble floor of the Edward and Henrietta St. George Hall were discussed at one of the meetings of the Central Committee. It was decided that this project was to be entrusted to Innocent Centorrino, our most capable Architectural Designer.
On November 8, Joe Spiteri worked on the dismantling of the concrete shuttering. The following day, Sunday, Twanny Callus cut the bezel into the wall and which will later support the concrete stairs leading to the roof. Mikiel Aquilina resumed work on the dismantling of the concrete shuttering and refined the bezel of the stairs. More work was carried out on the entablature.
On November 10, Salvu Magro did more work on the bezel of the stairs and, on the following day, Tuesday, the fifth entablature stone block was completed.
On November 17, Joe Spiteri, with the help of Karmnu Magro, Joseph Ellul, Joe Ellul and Karmenu Borg, started to erect the concrete shuttering for the stairs. This work was completed on November 28.
On November 29, more blocks were delivered to the site from the stone quarry. The lifting of these blocks onto the roof of the building was somehow hampered by inclement weather.
On Sunday, November 30, a group of volunteers took it upon themselves to collect all the debris and other unwanted material from the site. Anglu Ellul, Mario Mifsud, Mikiel Aquilina, Grezzju Farrugia and Karmenu Borg loaded a couple of trucks with this debris using a wheel-barrow. The work on the entablature resumed and the ninth block was now completed. Joe Spiteri worked on the erection of the concrete shuttering of the toilets.
On December 2, the reinforced concrete planks were placed in position on the intermediate floor while more work resumed on the sculpturing of various stone blocks - these blocks were later lifted onto the roof by a crane ready to be laid in position on top of the secondary facade.
On Friday, December 12, there was planned the pouring of concrete of the two flights of stairs, the layer above the roof planks and the toilet roofs. In spite of inclement weather, the work was carried out as planned - the people involved in this operation were issued with plastic raincoats. In addition to the pouring of concrete, a truck load of stone blocks and a consignment of concrete bricks were lifted onto the roof by a crane. Karmnu Magro, Felic Zerafa, Nikol Abdilla, Manwel Magro, Martin Formosa, Joseph Farrugia, Baskal Ellul, Joe Spiteri, Salvu Bugeja, Frans Zerafa, Joseph Ellul, Joe Zerafa, and Karmenu Borg worked hard and with great determination under difficult conditions of weather. It would be proper here to thank all those friends, especially Peter Caruana and Joseph Falzon, who loaned us all those tools and equipment that we needed and which facilitated the work involved considerably.
The following day, Saturday, Karmenu Caruana started on the laying of bricks - his efforts were halted however by bad weather conditions.
On Saturday, December 14, Karmenu Caruana together with a group of helpers resumed work on the uppermost room. In the meantime, the concrete shuttering was being dismantled. The sculpturing, which was kept on going without interruption, had now reached the fifteenth block. During the days close to Christmas, work was slowed down somewhat and this was due to the other activities organized by the Society. In spite of this, a truck load of bricks was delivered and lifted onto the roof together with a large quantity of sand and crushed stone. The bricks were used for the supporting walls while the other material was used for making and completed various stone blocks for the entablature - these blocks will ultimately rest on the upper six Doric columns.
|