|
Soon after 15th August 2001, the biggest and most important day in the Qrendi calendar, the Central Committee decided to resume work on the new club premises. On Tuesday, September 18, at Gawhra Hall a meeting was convened for all those individuals involved in the actual building of this magnificent edifice. Needless to say, for this meeting there was present Innocent Centorrino1 our clever and well known Architectural Designer. During the meeting, those present were briefed about the nature of the work planned for the next phase together with the administrative work involved. A discussion then ensued centering around safety on the job, the ordering of materials and other topics related to this ambitious project.
As from September 19, the orders for more stone blocks from the quarry were prepared together with the preparation for transferring to the site a number of large stone blocks which were stored on the club's property adjacent to Gawhra Hall. At around 8.00pm, club members loaded a number of stone blocks on to pallets ready to be transported from Gawhra Hall to the site of the new club premises In fact, on Tuesday, September 25 and with the aid of a Frida Transport forklifter. the stone blocks on pallets were loaded and transported to the site from Gawhra Hall on Felix' Zerafa's truck. The following day Wednesday. the crane hired from Mario Bondin (il-Manju) lifted the two steel beams that were assembled on the billiard hall roof and placed in their final position. In the same operation, the large stone blocks on pallets and the 9 inch stone blocks delivered from the quarry that same day, were lifted onto the roof of the billiard hall. On Friday, September 28, John Spiteri worked on a number of door-jamb stone blocks using the band-saw. On Sunday, September 30, Joe Spiteri continued with the work started earlier that week, that is, the erection of wooden shuttering around the steel beam reinforcing. In this regard, Joer was helped by Michael Aquilina and Joe Ellul. Later in the day, work had to be discontinued because of rain - While work continued on the shuttering. one for the 3 course steel beam and the other for the steel beam adjacent to it, it was decided the pouring of those beams was to be carried out on Saturday, October 6. At 7.30 that morning, Mario Bondins crane started work on the lifting of concrete purchased from Elbros – the pouring of these beams was supervised by Joe Spiteri. The entire operation only took 1.5 hour thanks to the special tools borrowed from various individuals.
|